Description
Cost Estimate ($)
Thompson Road - Storm sewer including curb and gutter (west of Cooper Lane)
$250,000
New Storm Sewer Highland Road (Woolastook to Calvin Lane) - Upper half
*75,000
Storm Sewer - Inglewood Drive Phase 1
*338,000
Inglewood/Nelson - Cross Culvert Connection
*15,000
New Storm Sewer/Curb & Gutter Central (Bustin Road to Young Street) (Private)
75,000
Eliminate North Street Drainage Channel
200,000
New Storm Sewer - Johnson Property to Crystal Court
35,000
New Storm Sewer - Baysong Bluff
15,000
New Storm Sewer - London Lane (Private)
15,000
Storm Drainage - South Avenue (Private)
15,000
Storm Sewer - Brookdale Avenue North Cross Culvert
40,000
Epworth Park West Storm Sewer Extension (Midwood to Brook)
25,000
Epworth Park West Storm Sewer Extension (Brook to Woolastook)
75,000
Maralyn Court Storm Sewer
100,000
Lacroix Drive Storm Sewer
55,000
Stevens Court Storm Sewer (Leighside to River Valley Drive)
70,000
Beverley Hills Drive (Storm Extension)
45,000
Woolastook Drive Storm Sewer Extension (Park to South of Valleyview)
100,000
Woolastook Drive Storm Sewer Extension (Valleyview to Evergreen)
250,000
Allingham & Birchwood - Storm Sewer and Catch Basin
10,000
Ash Glen Lane Drainage Improvement (Uncertain Status)
30,000
Total Cost - All Projects
$1,833,000



* Project Funded by Gas Tax Funding 2009