Category |
Location |
Cost Estimate ($) |
|
Sidewalk Renewal |
Woolastook Drive (Rte 177 South to Highland Road) |
15,000 |
|
|
Woolastook Drive (Highland Road to Allan St.) |
200,000 |
|
|
Replace existing broken panels (243m) Nerepis Road (2008 Carry Over) |
30,000 |
|
New Sidewalk & Curbs |
Woolastook Drive (June Ave. to River Valley Drive North) |
900,000 |
|
|
Inglewood Drive (Pamdenec to River Valley Drive) |
1,350,000 |
|
New Curbs |
Rosemere Drive (northern half - one side only) |
25,000 |
|
New Sidewalk in conjunction with Designated Highway Work |
River Valley Road (Epworth Park to Allingham Terrace) |
200,000 |
|
|
Nerepis Road (Ferry Road to Route 102) |
210,000 |
|
Total Curb & Sidewalk Cost |
|
$2,930,000 |